Friday, March 20, 2009

The Ditches are Finished



So after 30 days the ditches are done. This is how they are finished along the edge. I asked John how he planned to finish them off along the road edge and he says he hadn't thought of that. Apparently the contract with the men doing the ditches was to put in 2 feet of concrete. They did what they were contracted to do and now the edges are a disaster. I have posted a picture we took in a Panamanian development of a properly finished ditch edge but John at the meeting declared that our ditch edges would not be finished like that!



Friday, March 13, 2009

The Meeting

After some investigation we have discovered that it is unusual that so many titles should be released by MIVI (the watchdog for development) with so little infrastruture in place. In December of 2008 we decided that we needed to have a meeting with John and Rose to impress upon them the importance of finishing this development and finishing it in a timely fashion. It was our feeling that 2 and 1/2 years had been sufficient time to complete what they had started, even for amatures. In a formal letter we asked for a meeting with them at the end of January. The expectation was that they would have a timeline for completion of the work, including power, ditches, sidewalks and the park. We also requested to see a plan for the park complete with final elevations drawn up by professionals such as engineers and landscape architects.

The day of the meeting dawned and 2 days before Alfonso announced that he was unable to meet that day as it was his Sabbath (even though he had 2 months notice of the date). We rescheduled it out of respect for him to Feb 4.

The minutes of the meeting are as follows:


Minutes of Meeting with Representatives of Tropical Places
4 February 2009, David, Panama S.A.


This meeting was scheduled on 4 December 2008. The original date was set for 31 January but was moved to 4 February in respect for Alfonso Serrano’s Sabbath. A copy of the agenda is attached. The meeting commenced at 10:00 with Mr. John Wade, Mr. Alfonso Serrano, Mrs. Rose Ryan, Mrs. Rosalie Lillo and Mr. Harry Lillo.

Harry provided his perception of the matters to be discussed at the meeting including the purpose and expected outcomes. John questioned the additional items on the agenda. Harry explained that the two additional items were a further breakdown of two points and did not constitute new issues. Harry made it clear that although he was aware that other lot owners in the development shared the same concerns as we do, we were not here to represent any others, just ourselves.

When asked, John Wade stated that the three of them represented Tropical Place. When asked if there were any other partners he stated there are other partners but that was “classified information and can not be disclosed. In this meeting we represent Tropical Place”; no further discussion on the matter.

John Wade, Rose Ryan and Alfonso Serrano proceeded to admonish the Lillo’s for their conduct with respect to Tropical Places and were told they were ‘trouble makers’; in particular Rosalie with her emails in October and November to other lot owners. They were obviously upset that the Lillo’s had provided factual information on the state of the development to other lot owners. The Lillo’s were told that it would not be possible to maintain the personal friendships which the Lillo’s had expected to retain outside of these business dealings with Tropical Place. The Lillo’s in keeping with their commitment to maintain a professional approach to this meeting chose not to respond.

Receipts for payment on the Lots:
The first item of discussion was the issue of receipts for the purchase of the property. In 2008 Rosalie requested official receipts for the purchase of the Tropical Places property from Alfonso Serrano. Alfonso stated that he would provide them but needed to get official receipt documents which would take three days. These receipts were the subject of many emails through December and January. At one point Alfonso requested the exact amounts paid which suggested that receipts were forthcoming. However at this meeting Alfonso stated that it was impossible to issue such receipts for our purchase; the title was the only document that would be issued. Rose Ryan and John Wade also stated that they would not issue a receipt. Rose Ryan further stated that in Canadian real estate dealing, receipts are never issued; bank statements must be used to demonstrate the exchange of funds. In a question from Rosalie, Rose did admit that the lawyers in Canadian real estate dealings did provide a reconciliation of disbursements. Rose Ryan undertook to provide the Lillo’s with a photocopy of the bank draft that they used to pay for the lots. Harry stated that this information had been requested by our accountant and if necessary we would have Revenue Canada contact John Wade and Rose Ryan directly to confirm the amounts paid to them for these properties in Panama.

Rosalie noted the discrepancy between the amount paid for the property and the purchase amount shown on the titles. Alfonso attempted to explain Panamanian law as it relates to property assessment and taxation. He pointed out, as our lawyer; he believed it was in our best interest to have a minimal amount shown on our title in order to reduce our property taxes. (The amounts are approximately 1/10 of the purchase price). We had the right to request a reassessment following the completion of the house. The Lillo’s expressed a concern about capital gains they would need to pay in the event they decide to sell the property as the value on title was only a fraction of the price paid. Alfonso stated that he had done what was best for us.

UNDERTAKING:
Rose Ryan to provide the Lillo’s with a photocopy of their bank drafts for the three lots.

Ditches:
Approximately 30% of the concrete linings in the ditches were completed as of 4 February 2009; work had been suspended in early 2008. A contract has been let and concrete ditch construction is expected to be complete in 35 days (approximately March 15). The crew is about to begin construction. When asked how the tops of the ditches would be finished John stated that they would be finished to the edge of the road surface. Rosalie provided a picture of concrete ditches in a nearby Panamanian development which had a square curb edge on them and asked if this is how the edges would be finished at Tropical Places? John responded that that was not a Panamanian standard and would not be done at Tropical Places. There was then a question as to whether this development was to be completed to Panamanian standards or North American standards? At this point Juan Aguilera joined our meeting as legal representation for the Lillo’s. He had been delayed and was forced to join the meeting late.

North American or Panamanian construction standards for Tropical Places:

A discussion ensued as to whether there was an expectation that this development would be constructed to Panamanian or North American standards? John, Rose and Alfonso all stated emphatically that this development had always been reported to be to Panamanians standards and never expected to be to be to North American standards! The Lillos were told that if they had wanted to build in a development done to NA standards they should have bought in Valle Escondido or Los Molinos. John stated that Rosalie had only planted this idea that the development would be to North American standards in other lot owner’s minds and that this was never the stated intent of the developer. Rose Ryan stated that the roads were the only facility updated to North American standards. However upon further questions from Harry, Rose admitted that the road construction standards were the same as those set forth by the Panamanian regulators. The Lillo’s were told that for their $18,500 investment they should not expect anything more than a basic Panamanian development. The Lillo’s expressed that this was upsetting to them and believed it would be upsetting to other lot owners as well who they believed had higher expectations.

Roads:

The road construction is complete. When asked if the final topping of small crushed stone and a third coat of hot tar was going to be applied as seen in other Panamanian developments, John stated the roads were completed.

Sidewalks:
The Lillo’s asked when the developer was going to start construction of the sidewalks? John stated that was the responsibility of each lot owner. Alfonso went on to point out that he had to build the sidewalk in front of his own house in his upscale neighborhood. Harry indicated that it might be some time before everyone built their homes and therefore the network of sidewalks throughout the development would not be completed for quite some time. The Lillo’s then proceeded to show a copy of the Tropical Places development plan submitted to the Municipality. This plans clearly shows the design criteria for the sidewalks in the development; thereby the expectation that the developer would install the sidewalks. John accused the Lillo’s of obtaining the copy of the development plan from the engineer in charge and illegally obtaining ‘classified information’. Rosalie stated that this was a public document granted to her by the Municipality. John stated that he did not know if the sidewalks were the responsibility of the developer and would “take it under advisement”.

UNDERTAKING: At the end of the meeting John agreed to review the sidewalk requirements with the Municipality and advise the Lillo’s of the outcome of that meeting.


Water:
The domestic water system is now in place and working.

Electrical Power:
The power was promised in February 2008 and connected in January 2009. The developers could not explain the delay but blamed it on the power provider.
When asked if the Lillo’s could experience any issues with permanent electrical connection (perhaps because of an inadequate number of fire hydrants) they were told that all approvals were in place. Upon further discussion it was found that there had been some questioning about the number of hydrants by the bomberos. Rosalie asked to see a copy of the approvals to confirm that there would be no future problems. John and Alfonso stated that they did not have a document to confirm this. John and Alfonso agreed to check with the Fire Department to confirm that the current number of hydrants were satisfactory. John stated that if more hydrants were necessary Tropical Places would install them.

UNDERTAKING:
John Wade and Alfonso are to confirm with the fire department that the number of fire hydrants are adequate to have permanent power connected and there are no further impediments to permanent power connection. If necessary Tropical Places will install additional fire hydrants.

Park:
The rancho has been completed and Rose Ryan stated that there would be no further improvements on it such as tile or paint. She had planted four climbing vines at each corner of the rancho but obviously someone had stolen them. The Lillo’s pointed out the waste concrete from the rancho construction still remained around the base of each pillar and questioned where her topsoil and plants had been placed. She stated that she had placed them there along with 60 some odd other plants in the common area. The Lillo’s pointed out that it was difficult to see the evidence of these plantings on the common area.
The Lillo’s were pleased to hear that CESTA had been retained to prepare a professional plan for the common area including the pool and attendant infrastructure. This is to be completed in March 2009. Once completed it will be available for review at Tropical Places office (in the office of Alfonso Serrano). John stated that it is Tropical Places’ intent to implement the common area development and complete the common area and the pool as soon as possible.
The Lillo’s applauded Tropical Places commitment to complete this development in a timely manner.

UNDERTAKING: Tropical Places will advise lot owners of the availability of the common area plan and avail the plan to them.

Financial Assurance:
When asked, John indicated that sufficient funds exist to complete the development. Under “no circumstance” would Tropical Places be prepared to place funds in a trust account to facilitate the development of the common area and pool at a later date.

Release of Titles:
Alfonso indicated that all of the segregations of the lots are completed. The Lillo’s questioned if it was common for all segregations to be released with so little infrastructure in place in a development. Juan indicated that it was unusual that this would occur before work on the development was completed; however there are anomalies and circumstances where this could possibly occur in Panama.

Outstanding Debts:
Harry indicated that he was aware of at least one outstanding debt against the development. He asked if this type of debt could flow through to the lot owners. AS stated that the owners had their titles and the debt could not be attached to them. Juan pointed out that a debtor could attach liens to property owned by Tropical Places including the common area and unsold lots. We were assured that negotiations were underway to settle the outstanding debt and it would be taken care of in the week following this meeting.

Outstanding Regulatory Commitments:
Tropical Places has no outstanding regulatory commitments remaining. John stated that they have met all commitments.

Conclusion:
Harry thanked everyone for attending the meeting and stated that he would provide minutes from the meeting and a list of undertakings as agreed to at the conclusion of the meeting. The meeting concluded at 11:50.

You will note that Rose Ryan now states that the intent never was to do this development to North American standards. That it was always the intent to do the work to Panamanian standards, even though they have often laughed at the way things are done here in Panama. John stated that it was his intent to complete construction of the Park incuding pool ASAP, Rose is still maintaining that it will be done when there are sufficient houses to justify a pool. We maintain that we paid for a park with a pool and we would like a park with a pool. We will see what transpires. It is our observation based on past experience that what John and Rose say and what they do are often two different things.

Sunday, November 23, 2008

Homeowners Association

I am not sure where to even start this post but I would like to alert you to the truth regarding our pending Homeowners Association.


The truth is, that by Panamanian law, we do not have a development in the true sense of the word. In order to have a development, all homeowners must be in agreement at the time that they purchase the lots, with the covenants and restrictions registered with the development. These covenants and restrictions, in order to be effective, must be in Spanish and registered against the title of each lot, so that when the lot is sold the C&Rs go with it. If they are not registered at that time then, there is no development, the roads are public Panamanian property and it can be gated, but if someone complains the Municipality will make us take the gates down. Anybody is free to use the roads. There will be no restrictions regarding land use so that anyone could build a bamboo hut next to your half million dollar home. One could raise pigs or worse yet, fighting cocks that begin to crow at 3:00 AM and continue throught the day.


In order to change this situation and register the C&R's after the fact, each and every one of the lot owners must agree to accepting the C&R's and then allow them to be registered against the title to his/her lot. There is a $300 charge for registering them after the fact. If even ONE person of the 41 lot owners refuses to accept the C&R's, there will forever be no development. We can still have the park and the pool but there will be no Homeowners Association and no obligation to pay any maintenance fees. Some may chose to pay and some may not and there is no legal recourse to collect from those who refuse to pay. There will be no land use restrictions which could become a huge problem as the lots get sold off to others. We are pretty much all of the same mind at this time but others in the future may not be.

Sunday, November 16, 2008

Properly Finished Ditches

This is the way the ditches in our development are finished. I complained about the sloppy look along the edge and was told that they would be finished along the edge later. I am not sure who told me that if it was Alfonso or the guy that was doing the work, however....

in a local Panamanian development I saw ditches that look like this and it is my hope that our developers plan to finish off ours properly and that this expense does not fall upon us, the owners. Incidentally, in this development you can buy a small completed 3 br. 2 bath house finished to Panamanian standards for 40,000 including lot, and the development was finished properly BEFORE they built one house!

Monday, November 10, 2008

The Park: We've Been Dupped Folks

Yep! the park has been planted, see all the nice little trees. Make sure you double click so that you can see them better.

Check out your park bench!

Grounds squeeky clean - ya think?

Notice the tin falling off of the roof of the rancho, makes me want to get up there and party. Oh yes and that pile of leaves at the bottom of the hill, just picture a pool there with a little winding path up to the rancho.


This is the entrance to the lovely park.

For those of you involved in this development that follow my blog, you have probably become aware that we are embroiled in discussions with John and Rose about the state of the common areas, ditches and maintenance. I am now going to expose the truth to you in my next few posts. It would appear that we have been dupped as well as lied to about this whole project. We still do not have power and yet here is a note I got from Rose Ryan 10 months ago on Jan 21, 2008.

"Ivan was at the site on Sunday. Alfonso was there as we are to get the transformer and the water turned on. other than that, we are enjoying the condo....."

Fast forward to November the 9th - still no power!!

There has been much discussion about this issue of Homeowners Association fees. In a note that Rose Ryan sent to Linda M. recently Rose stated the following:

"Hi, I will try to respond,
Most of the development was done for 2007. It was an expectation - we
came close.The pool was always shown to be an item completed when there
are actual owners to enjoy it in a sufficient number to justify it. All
are in agreement. There is a gardening company that is keeping grass
etc. cut on a regular basis.
The construction costs are not born in any costs to the owners although
now that they are completed of course they will be. It is a private road
and our responsibility.The $350 is also a projection as there needs to
be maintanance, the common area space has been planted etc. Please go to
your google and look up our competition. The fees are multiple times
what ours are and charged MONTHLY. There is a lot of work and expence
envolved in doing a development."

Rose Ryan and John Wade undertook to do this development, sold us a piece, and it is not our problem if it turned out to be a lot more work and expense than they anticipated. The truth is we have been lied to. There is as yet no power, no park, no gardener, no nice plantings that are visible to the naked eye, nothing but dead grass, piles of rocks pushed up with overgrown grass and a little Rancho plopped on the top of the hill which is already falling apart as you can see by the tin flying off of the roof. I will say that there are 3 little palm trees planted near the entrance to the park that should be big in about 20 years or so and another 3 bigger ones along the main roadway at edge of Alfonso's lot.

This is your park and your homeowners fees will go towards maintaining it....enjoy...

Reality is Dawning

In 2006 my husband Harry and myself met John Wade and Rose Ryan through a mutual contact. John and Rose are a couple who are Realtors in Calgary, Alberta, Canada. They were promoting a development in Panama in which they had an interest. There would be, we were told, a pool, a rancho with cooking facilities for communal gatherings, a park with beautiful plants, a grand entrance with an arch overhead planted with bougainvilleas climbing it. I was taken out to Vale Escondido on my first trip here to view the scope of possibilities for landscaping and I was enchanted. Surely, if there was a paradise, this was it. We agreed to buy several lots from them. In 2007 they asked for the money even though they could not provide title. Being trusting souls we gave it to them.

Close to a year went by and we were now planing to begin construction of our dream home, save for one small problem, we still did not have title. As it turns out we did not have title because the engineer hired to do the development had not lived up to his end of the deal, or so we were told. The work done on the property was shoddy and apparently not up to standards. We were promised paved roads, we got gravel. The transformer poles were too short and needed to be replaced. There was insufficient transformer capacity. Consequently the developers were withholding payment for his services and in turn he was withholding segregation titles. After much fighting the titles to our lots were finally released in Jan 2008. At last we had title!

Subsequent to that he (the engineer) would not release any more titles until the developer completed his end of the deal. Completion of the ditches, park and common areas. So in Feb 2008 they commenced construction of the ditches. About 20 feet of ditch had been constructed by the time John and Rose left Panama to return to Canada. As the dust settled in their tracks the work stopped.

I came to Panama later in Feb that year and informed John that nothing was being done regarding the ditches. It turns out I believe that a stop work order had been placed. I stayed until the end of April and no more work was done during that time. When I returned in June, they were once again working on the ditches but now it was the rainy season and it is difficult, if not impossible to pour cement in a ditch if it is being washed away by rain. So construction of the ditches stopped. Less than half of the ditches are currently completed as I write this in mid November 2008.


I left again at the end of June with plans to return in September. Our return was delayed until late October. Rose and John had been here for 6 or 7 weeks in August and I was informed that Rose had commenced development of the Park. She had purchased and planted 60 some odd plants and had started an orchard behind our lots 19 and 34. Exciting news surely. Upon our return we were devastated to find that the park is nothing more than dead grass, oh yes, we did see the palm trees in the park, in fact there are 3 of them, the largest of which is about 2 feet tall. The orchard was never planted, that was a lie, and any other plants there I believe succumbed to roundup.


From the beginning of the development of the park I have tried to impress upon Rose Ryan the need for a plan for the common areas of this development. Just as you would not build a house without a plan it is my belief that there needs to be a plan in place for the park, entrance and any other common areas. I am referring to a plan drawn up by a landscape architect complete with engineered drawings of retaining walls, pools, rancho, etc. She consistently informs me that the park is a 'work in progress'. Anybody in Canada listening to her grandiouse plans would think that all was well in paradise. Well, news flash, it is not!!